Initial Challenge / Problem
Need for CO₂ removal and separation in a biogas upgrading system using scrubber and stripper columns.
| Industry of Client | Biogas / Renewable Energy (biogas upgrading systems) |
| Type of Pollutants | CO₂ |
| Material | 316L stainless steel |
| Design Features | – High number of discharge holes for uniform liquid distribution – Chimney trays and redistributors for improved mass transfer |
Project Location
Burnaby, Canada (Client HQ)
Brazil (Project installation location – Totara Plus)
Scale of Operation
Industrial-scale gas treatment system
60” diameter scrubber column
72” diameter stripper column
System Components / Customizations
Custom-designed column internals including:
– Liquid distributors (top and mid-bed)
– Flash gallery
– Multibeam support plates
– Feed pipe distribution system
Integration with Existing Systems
Internals designed to be installed inside existing vessels (Tags: PV01 and PV03), indicating retrofit integration.
Installation Timeline
– Drawings: ~3 weeks after order
– Fabrication: ~8 weeks after drawing approval
– Shipment: ~3–4 weeks after approved drawings
Special Considerations
– Factory Acceptance Testing (FAT) and QA/QC reports required
– Installation manuals and material traceability documentation required
– Packaging must meet international shipping standards (HT stamped wood)
– Portuguese documentation required for Brazil project